IH 30 @ Broadway Boulevard
Construction
Project Status
$1,748,344
Total Project Budget
$572,000
2019 Bond Funds
$1,176,344
Other Funds
Project Details
Project Description:
Intersection-widening improvements to relieve bottlenecks at intersection and adding northbound dual right-turn bays on Broadway Boulevard.
Proposition:
Council District(s):
Location(s):
Project Manager:
Doug Mikeworth (dmikeworth.aecom@garlandtx.gov)
Project Schedule
Design Start (Anticipated)
Early 2020Design End (Anticipated)
Early 2024Construction Start (Anticipated)
Early 2024Construction End (Anticipated)
Mid 2024
Design Start (Actual)
04/16/2020Design End (Actual)
11/21/2022Construction Start (Actual)
11/21/2022Construction End (Actual)
Comments