Lon Wynne Park
Complete
Project Status
$1,454,380
Total Project Budget
$642,880
2019 Bond Funds
$811,500
Other Funds
Project Details
Project Description:
Construction of a new splash pad at Lon Wynne Park.
Proposition:
Council District(s):
Project Manager:
Praneeth Tummala (ptummala.aecom@garlandtx.gov)
Project Schedule
Design Start (Anticipated)
Early 2021Design End (Anticipated)
Mid 2022Construction Start (Anticipated)
Mid 2022Construction End (Anticipated)
Mid 2023
Design Start (Actual)
04/13/2021Design End (Actual)
07/25/2022Construction Start (Actual)
07/25/2022Construction End (Actual)
09/04/2023
Comments