Meadowcreek Branch Park
Complete
Project Status
$283,725
Total Project Budget
$283,725
2019 Bond Funds
$0
Other Funds
Project Details
Project Description:
Get lost exploring Meadowcreek Branch Park's new wooden village, which includes a large double tower and a third, smaller play tower with a slide, ensuring fun for children of all ages. The additional swinging, climbing and spinning equipment enhance the play space with bonus recreational activities.
Proposition:
Council District(s):
Location(s):
Project Manager:
Praneeth Tummala (ptummala.aecom@garlandtx.gov)
Project Schedule
Design Start (Anticipated)
Mid 2020Design End (Anticipated)
Late 2021Construction Start (Anticipated)
Late 2021Construction End (Anticipated)
Late 2022
Design Start (Actual)
05/11/2020Design End (Actual)
11/01/2021Construction Start (Actual)
11/01/2021Construction End (Actual)
08/26/2022