Oaks Branch Greenbelt Park

Complete

Project Status

$212,000

Total Project Budget

$212,000

2019 Bond Funds

$0

Other Funds

Project Details

Project Description:

This nature-themed park is designed to blend seamlessly with its marsh-like, greenbelt surroundings. Boulder play and natural elements stimulate fun within the existing natural scenery.

Council District(s):

Location(s):

Project Manager:

Project Schedule

  • Design Start (Anticipated)

    Mid 2020
  • Design End (Anticipated)

    Early 2021
  • Construction Start (Anticipated)

    May 2021
  • Construction End (Anticipated)

    September 2021
  • Design Start (Actual)

  • Design End (Actual)

    02/24/2021
  • Construction Start (Actual)

    02/24/2021
  • Construction End (Actual)

    12/02/2021

Comments